DigDash Enterprise allows you to schedule automatic data refreshes.
Prerequisites
For the scheduling to work:
- the scheduler must be running: go to the Configuration -> Server Statuspage and check the scheduler’s status. If it is stopped, click on
.
- the scheduler user must be specified (the same as the supervisor). Initialisation must be carried out via the Configuration > Server Settings > Additional Settings > Schedules page. See the Schedules page for further details.
Scheduling refreshes
Refresh schedules can be set at three levels:
- Wallet
- Information flow
- Data model
By default, refreshes use the Default Schedule: automatic triggering every day at 8 pm.
You can change the settings for this default schedule in the Refresh Manager : the new settings will apply to any new roles created thereafter (they will not apply to existing roles), or create a new schedule.
For flows
For a wallet or flow, scheduling is carried out via the properties side panel under the Flows tab: select the wallet or flow from the list and go to the Scheduling tab in the side panel.
By default, flows are refreshed and synchronised at the same time as the information wallet. You can untick the ‘With wallet’ box and set a different schedule.

When the wallet (root of the tree structure) is selected, the interface distinguishes between the schedule for the wallet itself and the schedules for the flows contained within the wallet.
In the ‘Schedule’ section, all flows schedules are selected. You can change the schedule for all flows.

For data models
For a data model, scheduling is carried out via the Refresh tab in the data model configuration window.

For a selection of data models, scheduling is carried out via the ‘Configure multiple data models’ dialog box, which is displayed by right-clicking and selecting ‘Edit…’ from the context menu.

Adding/editing a schedule
To create a new refresh schedule:
- In the case of a wallet or data flow, first deselect the ‘With wallet’ tick box.
- Click the + button.
➡ The Schedule dialogue box appears .
- From the Trigger drop-down list, select the refresh type and configure the corresponding settings (click the link for more details on configuring each type):
- You can save the defined schedule as a shared schedule. A shared refresh schedule is a schedule that is saved and can be used to schedule the refresh of other items. It can be shared within a role or across all roles. To do this:
- Tick the ‘Save as a shared schedule...’ box
- Enter a name and select the role with which you wish to share the refresh schedule, or select ‘None’ to share it with all roles.
See the page Refresh Manager for more details on shared refresh schedules.
- Click OK.
➡ The schedule is added to the list of schedules.
To edit a refresh schedule, select it, click the
and change the settings as required.
Deleting a schedule
To delete a refresh schedule, select it and click the
button